【Report】Tsuyama City Kuwadani ELIS Power Plant-(2) Installation of control panel-

2018/10/31


[Report] Tsuyama City Kuwadani ELIS Power Station- (1) Control panel foundation work-

On October 29, 2018, we installed the control panel. (Photo 1-6)

13
Photo1 The wiring from the generator is buried underground.

14
Photo2 The wiring from the generator goes out from the underground to the control panel.

15
Photo3 It seems that an anchor hole for fixing the control panel is made in the foundation.

16
Photo4 It seems that an anchor for fixing the control panel is being driven into the foundation.

17
Photo5 The control panel is fixed and the construction is completed.

Next time, a test run is scheduled for early November.

The EV can be charged using electricity generated only by mini hydroelectric power generation of natural energy, and the generated electricity can be used for charging mobile phones and the like in the event of a disaster.